Lucas v. Algonquin Gas Transmission Co.
Supreme Court of Connecticut
1Opinion of the CourtWynne, J.
In this action the plaintiffs seek to recover damages for substantial injury claimed to have been caused by the condition in which property outside the bounds of the named defendant’s right of way was left after the construction of a pipe line. The appeal is from a judgment for the defendants rendered by the Superior Court. The suit was brought against the named defendant, hereinafter called Algonquin, and the contractor which performed the work. By stipulation, the appeal is determinative of the issues of a similar action disposed of by the trial court and also appealed to this court. No…