D'Amario v. Connor Construction, Inc.
Massachusetts District Court, Appellate Division
1Opinion of the CourtFlynn, J.
This is an action in contract in which the plaintiff seeks to recover $ 1,002.122 as an alleged balance due for work performed under a subcontract with the defendant.
Summary judgment was entered in the District Court Department for the plaintiff. The pleadings, affidavits and other documents upon which said summary judgment was based reveal the following:
On June 20, 1973 the parties executed a written subcontract whereby the plaintiff agreed to perform certain plumbing work for the defendant. Thereafter, a dispute arose between the parties as to which of them was required to perform certain…
2Cases cited8 opinions
- Community National Bank v. DawesMassachusetts Supreme Judicial Court · 1976
- In Re the Arbitration Between Lipschutz & GutwirthNew York Court of Appeals · 1952
- Stop & Shop Companies, Inc. v. Gilbane Building Co.Massachusetts Supreme Judicial Court · 1973
- Agoos Kid Co. v. Blumenthal Import Corp.Massachusetts Supreme Judicial Court · 1933
- Doral Country Club, Inc. v. O'CONNORMassachusetts Supreme Judicial Court · 1968
3 more not listed; retrieve them via the Exa API.