Public Utility Commission of Texas v. City of Corpus Christi
Court of Appeals of Texas
1Opinion of the Court
OPINION
McDONALD, Chief Justice.
This is an appeal by the Public Utility Commission of Texas, and Central Power & Light Company from temporary injunction enjoining PUC from enforcing an Interim Rate Order (and the Interim Order Nunc Pro Tunc), and enjoining CPL from charging rates pursuant to such orders. The effectiveness of the temporary injunction was suspended pending final hearing upon CPL posting bond to refund ratepayers if they finally be entitled to same.
CPL gave appellee cities “Statement of Intent” to increase its electric utility rates, (as well as all cities served by its entire…
2Cases cited11 opinions
- Lone Star Gas Co. v. StateTexas Supreme Court · 1941
- Muskogee Gas & Electric Co. v. StateSupreme Court of Oklahoma · 1920
- Sproles Motor Freight Line, Inc. v. SmithCourt of Appeals of Texas · 1939
- Texas Air Control Board v. Travis CountyCourt of Appeals of Texas · 1973
- Chicago Railways Co. v. City of ChicagoIllinois Supreme Court · 1920
6 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- City of Corpus Christi v. Public Utility Commission of TexasTexas Supreme Court · 1978
- B & B Auto Supply, Sand Pit, and Trucking Co. v. Central Freight Lines, Inc.Texas Supreme Court · 1980
- Central Power & Light Co. v. Del Mar Conservation DistrictCourt of Appeals of Texas · 1980
- Application of Northwestern Bell Tel. Co.South Dakota Supreme Court · 1982
- Potlatch Corp. v. Missouri Pacific RailroadSupreme Court of Arkansas · 1995
8 more not listed; retrieve them via the Exa API.