McBro Planning and Development Company and McCarthy Brothers Company, a Joint Venture v. Triangle Electrical Construction Company, Inc.
Court of Appeals for the Eleventh Circuit
1Opinion of the Court
EDWARD S. SMITH, Circuit Judge:
Defendant-appellant, Triangle Electrical Construction Company, Inc. (Triangle), appeals here from the United States District Court for the Northern District of Alabama, which granted the petition of plaintiffs-appellees (McBro) for an order compelling arbitration and staying further proceedings in the state court. We affirm.
Background
This suit concerns the arbitrability of Triangle’s claims, cast in tort, against McBro, with whom Triangle had no written arbitration agreement. Both Triangle and McBro did have written arbitration agreements with St. Margaret’s…
2Cases cited2 opinions
- Janmort Leasing, Inc. v. Econo-Car International, Inc.District Court, E.D. New York · 1979
- Federal Mogul Corp. v. Universal Const. Co.Court of Civil Appeals of Alabama · 1979
3Cited by143 opinions
- Thomson-Csf, S.A. v. American Arbitration Association, Evans & Sutherland Computer CorporationCourt of Appeals for the Second Circuit · 1995
- Grigson v. Creative Artists Agency, L.L.C.Court of Appeals for the Fifth Circuit · 2000
- International Paper Company v. Schwabedissen Maschinen & Anlagen GmbhCourt of Appeals for the Fourth Circuit · 2000
- E.I. DuPont de Nemours and Co. v. Rhone Poulenc Fiber and Resin Intermediates, S.A.S.Court of Appeals for the Third Circuit · 2001
- Sunkist Soft Drinks, Inc., Del Monte Corporation, Nabisco Brands, Inc. v. Sunkist Growers, Inc.Court of Appeals for the Eleventh Circuit · 1993
138 more not listed; retrieve them via the Exa API.