Eastside Disposal Co. v. City of Mercer Island
Court of Appeals of Washington
1Opinion of the CourtHorowitz, J.
— Eastside Disposal Company, a competing bidder for a 5-year garbage collection contract, attacks the validity of the contract awarded to General Disposal Company by the City of Mercer Island. The issue raised is whether the absence of General’s signature on its successful bid proposal is a waivable informality when the bid proposal refers to the accompanying bid bond and that bond in turn refers to the bid proposal, the bond being signed by the bidder and its surety. The trial court held the absence of the signature on the bid proposal was not an informality which could be waived. It…
2Cases cited10 opinions
- Thibodeaux v. ThibodeauxSupreme Court of Louisiana · 1904
- Interstate Power Co. v. Town of McGregorSupreme Court of Iowa · 1941
- Whitemarsh Township Authority v. Finelli Bros.Supreme Court of Pennsylvania · 1962
- City of Spokane v. CarlsonWashington Supreme Court · 1968
- A.A.B. Electric, Inc. v. Stevenson Public School District No. 303Court of Appeals of Washington · 1971
5 more not listed; retrieve them via the Exa API.
3Cited by6 opinions
- Spawglass Construction Corp. v. City of Houston, Texas Court of Appeals, 14th District (Houston)1998
- Menefee v. County of FresnoCalifornia Court of Appeal · 1985
- State v. JohnsonIdaho Supreme Court · 1975
- Centric Corporation v. Barbarossa & Sons, Inc.Wyoming Supreme Court · 1974
- Farmer Construction, Ltd. v. StateWashington Supreme Court · 1983
1 more not listed; retrieve them via the Exa API.