Robinson v. United States
Supreme Court of the United States
1Opinion of the Court
Mr. Justice Brandéis
delivered the opinion of the Court.
On August 30, 1905, claimant’s intestate entered into a contract with the United States to instal the interior fin ish in the custom house building then being constructed in New York City pursuant to Act of March 2, 1899, c. 337, 30 Stat. 969. The contract price was $1,037,-281.69; and the time for completion of the work, October 15, 1906. • Before it had been completed, but after that date, a supplemental agreement was made, which provided for additional work; increased the contract price $200,041.01; and extended the time for completion…
2Cases cited11 opinions
- United States v. SpearinSupreme Court of the United States · 1918
- Sun Printing and Publishing Assn. v. MooreSupreme Court of the United States · 1902
- United States v. Bethlehem Steel Co.Supreme Court of the United States · 1907
- United States v. Atlantic Dredging Co.Supreme Court of the United States · 1920
- Wise v. United StatesSupreme Court of the United States · 1919
6 more not listed; retrieve them via the Exa API.
3Cited by37 opinions
- Priebe & Sons, Inc. v. United StatesSupreme Court of the United States · 1947
- Mega Construction Co. v. United StatesUnited States Court of Federal Claims · 1993
- Psaty & Fuhrman, Inc. v. Housing AuthoritySupreme Court of Rhode Island · 1949
- George Sollitt Construction Co. v. United StatesUnited States Court of Federal Claims · 2005
- ACE Constructors, Inc. v. United StatesUnited States Court of Federal Claims · 2006
32 more not listed; retrieve them via the Exa API.