This was an action by a materialman on a public contractor’s bond. Judgment was for plaintiff. Defendant appeals.
The contractor entered into a contract December 13,1930, to build certain sewers. This job was No. 59. The date of the contract was October 13, 1930. He gave the bond under R. S. 60-1413, and entered into a contract with plaintiff for certain materials. The materials were shipped, and Snyder agreed to pay $2,100.22 for *147them. He paid $1,000 but did not pay the balance. This suit was started June 25, 1931, against the surety company…
2Cases cited14 opinions
- Gorrell v. BattelleSupreme Court of Kansas · 1914
- Taylor v. Swift & Co.Supreme Court of Kansas · 1923
- Beneke v. Bankers Mortgage Co.Supreme Court of Kansas · 1925
- Union Pacific Railroad v. SweetSupreme Court of Kansas · 1908
- Unit Sash & Sales Co. v. EarlySupreme Court of Kansas · 1925
9 more not listed; retrieve them via the Exa API.
3Cited by4 opinions
- Culver v. Mid-Continent Casualty CompanySupreme Court of Oklahoma · 1974
- OTTAWA PLUMBING, HEATING & AIR CONDITIONING CO v. MooreSupreme Court of Kansas · 1962
- Ottawa Plumbing, Heating & Air Conditioning, Inc. v. MooreSupreme Court of Kansas · 1962
- Joplin Cement Co. v. White-Layton Mechanical Contractors, Inc.Supreme Court of Kansas · 1960