Legal Opinion
General Electric Co.
United States Court of Claims
Decided April 7, 1978No. 188-75PublishedCited by 2 opinions
1Opinion of the Court
"This matter comes before the court on third-party defendant Honeywell’s request for prompt review, pursuant to Rule 53(c), of Trial Judge Browne’s interlocutory order (of March 14, 1978) insofar as that order denies discovery of plaintiffs documents numbered 1, 4, 5, 9, 14, 17, 25, 26, 27, 32, and 38. Because we find the matters alleged by Honeywell to be insufficient to warrant prompt review by the court, we deny Honeywell’s request.
"We note at the outset that this action has already been delayed by questions of disqualification of counsel and of the Trial Judge and has previously been…
2Cases cited3 opinions
- General Electric Co.United States Court of Claims · 1977
- PetrofskyUnited States Court of Claims · 1975
- SteenUnited States Court of Claims · 1976
3Cited by2 opinions
- Knogo Corp. v. United StatesUnited States Court of Claims · 1981
- C.P. Squire Contractors, Inc. v. United StatesUnited States Court of Claims · 1982