1Opinion of the CourtSeinfeld, C.J.
A jury determined that the State Department of Transportation caused Kiewit-Grice to sustain damages in the amount of $1,511,959. The trial court then awarded Kiewit-Grice prejudgment interest on the award. The State appeals. We reverse.
Facts
In 1984, the Department contracted with the joint venture Kiewit-Grice to construct concrete bridge pontoons for the third Lake Washington floating bridge. The contract required that the pontoons be built according to the Department’s specifications. It also called for two separate construction cycles, "Cycle I” and "Cycle II”, during each of which the…
2Cases cited19 opinions
- Prier v. Refrigeration Engineering Co.Washington Supreme Court · 1968
- Hansen v. RothausWashington Supreme Court · 1986
- Gardner v. MaloneWashington Supreme Court · 1962
- State v. ParkerWashington Supreme Court · 1901
- Cumbie v. CumbieWashington Supreme Court · 1963
14 more not listed; retrieve them via the Exa API.
3Cited by28 opinions
- State v. ElmoreWashington Supreme Court · 1999
- Litho Color, Inc. v. Pacific Employers InsuranceCourt of Appeals of Washington · 1999
- Polygon Northwest Co. v. American National Fire InsuranceCourt of Appeals of Washington · 2008
- Flint v. HartCourt of Appeals of Washington · 1996
- SCOCCOLO CONST. v. City of RentonWashington Supreme Court · 2006
23 more not listed; retrieve them via the Exa API.