Midsouth Steel, Inc. v. DPR Construction, Inc.
District Court, D. South Carolina
1Opinion of the Court
ORDER
Richard Mark Gergel, United States District Court Judge
This matter is before the Court on the parties’ motions for summary judgment. (Dkt. Nos. 7, 26). For reasons discussed below, the Court DENIES Defendants’ motion for summary judgment (Dkt. No. 7) and GRANTS in part and DENIES in part Plaintiffs motion for summary judgment (Dkt. No. 26).
I. Background
This matter arises out of a hotel construction project in Charleston, South Carolina. Defendant DPR Construction, Inc. was the general contractor on the project. On November 15, 2013, Defendant subcontracted the “Structural Steel,…
2Cases cited8 opinions
- Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
- Williams v. TaylorSupreme Court of the United States · 2000
- George F. Thompson v. Potomac Electric Power CompanyCourt of Appeals for the Fourth Circuit · 2002
- Hodges v. RaineySupreme Court of South Carolina · 2000
- Phillips v. CSX Transportation, Inc.Court of Appeals for the Fourth Circuit · 1999
3 more not listed; retrieve them via the Exa API.