K-Con Building Systems, Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
Trial; Contract to Design and Build Prefabricated Metal Building; RCFC 15; Futility of Supplemental Complaint; Contract Disputes Act of 1978; Remission of Liquidated Damages; Counterclaim for Liquidated ■ Damages; Contractual Notice Requirement; Abandoned Claim; Excusable Delay; Critical Path; Affirmative Defenses
OPINION AND ORDER
SWEENEY, Judge
Plaintiff K-Con Building Systems, Inc. contracted with the United States Coast Guard (“Coast Guard”) to design and construct a prefabricated metal building in Elizabeth City, North Carolina. Because plaintiff did not complete construction by the…
2Cases cited53 opinions
- Foman v. DavisSupreme Court of the United States · 1962
- Pace v. DiGuglielmoSupreme Court of the United States · 2005
- Holland v. FloridaSupreme Court of the United States · 2010
- Irwin v. Department of Veterans AffairsSupreme Court of the United States · 1991
- Griffin v. School Bd. of Prince Edward Cty.Supreme Court of the United States · 1964
48 more not listed; retrieve them via the Exa API.
3Cited by8 opinions
- DNC Parks & Resorts at Yosemite, Inc. v. United StatesUnited States Court of Federal Claims · 2017
- Aegis Defense Services, LLC, f/k/a Aegis Defence Services Ltd.Armed Services Board of Contract Appeals · 2017
- ECC International LLCArmed Services Board of Contract Appeals · 2021
- Lcc-Mzt Team IV v. United StatesUnited States Court of Federal Claims · 2021
- Marine Industrial Construction, LLC v. United StatesUnited States Court of Federal Claims · 2022
3 more not listed; retrieve them via the Exa API.