Legal Opinion

ARC & Gas Welder Associates, Inc. v. Green Fuel Economizer Co.

Court of Appeals for the Fourth Circuit

Decided December 30, 1960No. 8186PublishedCited by 7 opinions

1Opinion of the Court

SOPER, Circuit Judge.

This case concerns a dispute between a subcontractor and a sub-subcontractor as to which one of them was obliged to do certain work in the performance of a government contract. Blount Bros. Construction Company, a co-partnership of the State of Alabama, the prime contractor, entered into a general contract with the United States, acting through the Department of the Army, on June 30, 1955, to construct two stainless steel cloud chambers in a biological laboratory at Camp Detrick, Frederick, Maryland. On July 28, 1955, Blount entered into a subcontract with the Green Fuel…

2Cases cited5 opinions

  1. Freeman v. Stanbern Construction Co.Court of Appeals of Maryland · 1954
  2. Applestein v. Royal Realty Corp.Court of Appeals of Maryland · 1942
  3. Appleman v. FisherCourt of Appeals of Maryland · 1871
  4. Insley v. MyersCourt of Appeals of Maryland · 1949
  5. United States v. BlountDistrict Court, D. Maryland · 1960

3Cited by7 opinions

  1. Commercial Insurance Company of Newark, New Jersey v. Hector GonzalezCourt of Appeals for the First Circuit · 1975
  2. Glassman Const. Co., Inc. v. Maryland City Plaza, Inc.District Court, D. Maryland · 1974
  3. Huang International, Inc. v. Foose Construction Co.Wyoming Supreme Court · 1987
  4. Acme Process Equipment Co. v. United StatesCourt of Appeals for the First Circuit · 1965
  5. Arc & Gas Welder Associates, Inc. v. Green Fuel Economizer Co.Court of Appeals for the Fourth Circuit · 1960

2 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API