Adam Groth & Co. v. Goss & Guise
Appellate Court of Illinois
1Opinion of the CourtJustice McSurely
Plaintiff brought suit to recover damages on account of defendant’s alleged breach of a contract to furnish labor and material in connection with the construction of a school building at Joliet, Illinois. It was stipulated that the amount of damages was $2,117.96. At the close of plaintiff’s case, upon motion, the court directed the jury to return a verdict in favor of defendant and from the judgment that plaintiff take nothing it appeals.
September 22, 1919, plaintiff entered into a written contract with the Board of School Inspectors of District 86, Will County, Illinois, to erect the…
2Cases cited9 opinions
- City of Elgin v. JoslynIllinois Supreme Court · 1891
- Kelly v. CarrollAppellate Court of Illinois · 1921
- Christopher & Simpson Architectural Iron & Foundry Co. v. E. A. Steininger Construction Co.Missouri Court of Appeals · 1918
- Klaub v. VokounAppellate Court of Illinois · 1912
- Andalman v. Chicago & Northwestern Railway Co.Appellate Court of Illinois · 1910
4 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Traff v. FabroAppellate Court of Illinois · 1949
- Consumers Construction Co. v. County of CookAppellate Court of Illinois · 1971