Board of Education v. Sandman
New York Supreme Court
1Opinion of the CourtTownley, J.
On January 4, 1922, defendant Sandman contracted with the plaintiff to do some general repairs, painting, etc., in a public school in the city of New York for the agreed contract price of $805, the work to be finished within ninety days after the contractor was notified to commence work. On May 10,1922, plaintiff duly notified said contractor to commence work, but Sandman never performed any of the work and abandoned the contract. On March 27, 1924, plaintiff duly awarded a new contract for the same work to another contractor for the agreed contract price of $973, and such other contractor…
2Cases cited5 opinions
- Mosler Safe Co. v. Maiden Lane Safe Deposit Co.New York Court of Appeals · 1910
- Ward v. Hudson River Building Co.New York Court of Appeals · 1891
- Village of Canton v. Globe Indemnity Co.Appellate Division of the Supreme Court of the State of New York · 1922
- Gallagher v. BairdAppellate Division of the Supreme Court of the State of New York · 1900
- Murphy v. . United States Fidelity and Guaranty CompanyNew York Court of Appeals · 1906
3Cited by3 opinions
- Six Companies of California v. Joint Highway Dist. No. 13Court of Appeals for the Ninth Circuit · 1940
- Clemente Construction Corp. v. P. T. Cox Contracting Co.New York Supreme Court · 1939
- Teck v. Board of EducationAppellate Division of the Supreme Court of the State of New York · 1935