National Brick & Supply Co. v. Baylor
Court of Appeals for the D.C. Circuit
1Opinion of the Court
EDGERTON, Circuit Judge.
Areawide Building Corporation contracted with appellees, the trustees of Mount Joy Baptist Church, to make alterations and additions to the church building, payment to be made in installments as the work progressed. Areawide abandoned the work after several payments had been made. Article 10 of the contract provided: “Should the Contractor neglect to prosecute the work properly, or fail to perform any provision of the contract, the Owner, after seven days’ written notice to the Contractor, may. without prejudice to any other remedy he may have, * * * terminate the…
2Cases cited4 opinions
- Van Winkle v. CrowellSupreme Court of the United States · 1892
- Carey v. CyrSupreme Judicial Court of Maine · 1955
- Riggs Fire Insurance v. SheddCourt of Appeals for the D.C. Circuit · 1900
- Winter v. Hazen-Latimer Co.District of Columbia Court of Appeals · 1914
3Cited by4 opinions
- National Brick & Supply Company, Inc., a Corporation v. William E. Baylor, Trustees of Mount Joy Baptist Church, Abraham Grunstein, Abraham Fix, and Louis Nadelman, Partners, T/a Columbia Building Products Company v. William E. Baylor, Trustees of Mount Joy Baptist ChurchCourt of Appeals for the D.C. Circuit · 1962
- Moore v. AxelrodDistrict of Columbia Court of Appeals · 1982
- National Brick & Supply Co. v. BaylorCourt of Appeals for the D.C. Circuit · 1963
- National Brick & Supply Company, Inc., and Hudson Supply & Equipment Company v. William E. Baylor, Trustees, Mt. Joy Baptist Church, Abraham Grunstein, Partners, T/a Columbia Building Products Company v. William E. Baylor, Trustees, Mt. Joy Baptist ChurchCourt of Appeals for the D.C. Circuit · 1963