Seldon Construction Co. v. Dowell
Supreme Court of Oklahoma
1Opinion of the CourtCorn, J.
This action was commenced by the plaintiff in error, Seldon Construction Company, plaintiff below, to foreclose a materialman’s lien upon a claim in the sum of $3,749.34 against a house and lot owned by the defendant Nell M. Dowel 1, in the town of Red Fork, in Tulsa county.
Stephenson - Browne Lumber Company intervened and asked judgment for $1,092.65 and attorney’s fees and costs, and Ellison Plumbing & Heating Company also intervened, asking judgment in the sum of $515 and attorney’s fees and costs.
The contract sued upon was admittedly an oral contract, and was for the removal and repair of…
2Cases cited3 opinions
- Garrison Coal Co. v. SempleSupreme Court of Oklahoma · 1921
- Sand Springs R. Co. v. SmithSupreme Court of Oklahoma · 1921
- Wetzel v. RixseSupreme Court of Oklahoma · 1923
3Cited by2 opinions
- Wineland v. JonesSupreme Court of Oklahoma · 1943
- Smoot v. AnthonySupreme Court of Oklahoma · 1943