1Opinion of the CourtCorn, J.

This action was commenced by the plaintiff in error, Seldon Construction Company, plaintiff below, to foreclose a materialman’s lien upon a claim in the sum of $3,749.34 against a house and lot owned by the defendant Nell M. Dowel 1, in the town of Red Fork, in Tulsa county.

Stephenson - Browne Lumber Company intervened and asked judgment for $1,092.65 and attorney’s fees and costs, and Ellison Plumbing & Heating Company also intervened, asking judgment in the sum of $515 and attorney’s fees and costs.

The contract sued upon was admittedly an oral contract, and was for the removal and repair of…

2Cases cited3 opinions

  1. Garrison Coal Co. v. SempleSupreme Court of Oklahoma · 1921
  2. Sand Springs R. Co. v. SmithSupreme Court of Oklahoma · 1921
  3. Wetzel v. RixseSupreme Court of Oklahoma · 1923

3Cited by2 opinions

  1. Wineland v. JonesSupreme Court of Oklahoma · 1943
  2. Smoot v. AnthonySupreme Court of Oklahoma · 1943