Order unanimously affirmed without cost. Memorandum: State Finance Law § 137 (3) created a cause of action in favor of a material-man against moneys due or to become due to a contractor pursuant to its contract with the State where one did not otherwise exist. It is a condition precedent to bringing the action that written notice of the claim be given within 120 days from the date on which the last of the material was furnished. The notice must be served either by personal delivery or by registered mail (Ulster Elec. Supply Co. v Maryland Cos. Co., 35 AD2d 309, 310, affd 30 NY2d 712). The…

2Cases cited2 opinions

  1. Ulster Electric Supply Co. v. Maryland Casualty Co.Appellate Division of the Supreme Court of the State of New York · 1970
  2. Ulster Electric Supply Co. v. Maryland Casualty Co.New York Court of Appeals · 1972

3Cited by2 opinions

  1. Conesco Industries, Ltd. v. St. Paul Fire & Marine InsuranceAppellate Division of the Supreme Court of the State of New York · 1992
  2. Beer-Four Transportation Corp. v. Zurich American InsuranceAppellate Division of the Supreme Court of the State of New York · 2010