Hunt, C.J. —

Geo Exchange Systems, LLC (GES), and Total Energy Concepts, Inc. (TECI), appeal the trial court’s reduction of a private construction lien claim, which the trial court deemed excessive under RCW 60.04.081 by approximately $1 million. GES and TECI argue that the trial court erred in (1) ruling that the statute of limitations in RCW 60.04.141 extinguished TECI’s right to collect the $1 million, which had been the subject of an earlier expired lien, and (2) reducing the later lien in a summary proceed*627ing. GES and TECI also seek attorney fees and costs under RCW 60.04.081(4) and RAP…

2Cases cited11 opinions

  1. Curtis Lumber Co. v. SortorWashington Supreme Court · 1974
  2. Lane v. Department of Labor & IndustriesWashington Supreme Court · 1944
  3. Nghiem v. StateCourt of Appeals of Washington · 1994
  4. W.R.P. Lake Union Ltd. Partnership v. Exterior Services, Inc.Court of Appeals of Washington · 1997
  5. Farwest Steel Corp. v. Mainline Metal Works, Inc.Court of Appeals of Washington · 1987

6 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Shelcon Construction Group, LLC v. HaymondCourt of Appeals of Washington · 2015
  2. Geo Exchange Systems, LLC v. CamCourt of Appeals of Washington · 2003
  3. Shelcon Construction Group v. Scott HaymondCourt of Appeals of Washington · 2015