Legal Opinion

Stanley Newman Co. v. City of Boston

Massachusetts Supreme Judicial Court

Decided June 27, 1935Published

1Opinion of the CourtLummus, J.

This is a bill in equity by a subcontractor on a schoolhouse, to obtain payment out of security furnished by the contractor under G. L. (Ter. Ed.) c. 149, § 29. The only question is the amount due. The judge ruled that the plaintiff had performed its contract, and entered a decree for the balance unpaid. The contractor appealed.

The subcontract required the plaintiff to do the waterproofing, and the “Dampproofing to the interior surfaces of all exterior walls. ... All the above work to comply with the general specifications and according to Sect. 5 Pg. 65 to Pg. 68 inclusive and all other work…

2Cases cited19 opinions

  1. Stoops v. SmithMassachusetts Supreme Judicial Court · 1868
  2. Swett v. ShumwayMassachusetts Supreme Judicial Court · 1869
  3. A. J. Tower Co. v. Southern Pacific Co.Massachusetts Supreme Judicial Court · 1904
  4. West End Manufacturing Co. v. P. R. Warren Co.Massachusetts Supreme Judicial Court · 1908
  5. Lynn Safe Deposit & Trust Co. v. AndrewsMassachusetts Supreme Judicial Court · 1902

14 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API