Blauner Construction Co. v. United States
United States Court of Claims
1Opinion of the CourtWhaley, Chief Justice
The plaintiff entered into a written contract with the defendant through the head of the Procurement Division,, Treasury Department, on July 12, 1937, under which it undertook to furnish all labor and materials for the construction of a new post office building at Orange, Massachusetts,, in strict accordance with the plans and specifications, for the price of $47,740 for the work complete. The work was to be finished within 300 calendar days from receipt of notice to proceed. This notice was given on July 30, 1937, which fixed the completion date as May 27,1938. Before bids were called the…
2Cases cited1 opinion
- C. W. Blakeslee & Sons, Inc. v. United StatesUnited States Court of Claims · 1939
3Cited by8 opinions
- Flippin Materials Co. v. United StatesUnited States Court of Claims · 1963
- Weeks Dredging & Contracting, Inc. v. United StatesUnited States Court of Claims · 1987
- Alvin H. Leal, Trading as Plains Construction Company, and Mercantile National Bank at Dallas, a Corporation v. United StatesUnited States Court of Claims · 1960
- Leal v. United StatesUnited States Court of Claims · 1960
- A. Teichert & Son, Inc. v. State of Cal.California Court of Appeal · 1965
3 more not listed; retrieve them via the Exa API.