United States v. Buffalo Pitts Co.

Court of Appeals for the Second Circuit

Decided January 29, 1912No. 139PublishedCited by 3 opinions

lu Error to the Circuit Court of the United States for the Western District of New York. Action by the Buffalo Pitts Compauy against the United States. There was a judgment for plaintiff, and defendant brings error.

1Opinion of the Court

WARD, Circuit Judge.

This is a writ of error to a judgment of the Circuit Court sitting as a court of claims under the Tucker act cf March 3, 1887 (24 Stat. ¿05), in favor of the plaintiff and against *906the United States. The government had under the reclamation act of June 17, 1902 (32 Stat. 388), entered into a contract with the Taylor-Moore Construction Company to build the Hondo dam in connection with the Plondo project in New Mexico. Section 7 of that act provides:

“That where in carrying out the provisions of this act it becomes necessary to acquire any rights or property, the Secretary of…

2Cases cited11 opinions

  1. Kohl v. United StatesSupreme Court of the United States · 1876
  2. United States v. LynahSupreme Court of the United States · 1903
  3. Dooley v. United StatesSupreme Court of the United States · 1901
  4. Langford v. United StatesSupreme Court of the United States · 1880
  5. Roberts v. Northern Pacific RailroadSupreme Court of the United States · 1895

6 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Seven Lakes Reservoir Co. v. MajorsSupreme Court of Colorado · 1921
  2. J. G. White & Co. v. Ball Engineering Co.Court of Appeals for the Second Circuit · 1915
  3. International Harvester Co. of America v. United StatesUnited States Court of Claims · 1931

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API