Noble J. Dick, Inc. v. Warburton
Supreme Court of Delaware
1Per curiam
This appeal brings up for review an order of the Superior Court, entered on cross-motions for summary judgment. The effect of the order is to validate an indemnification agreement and defer until trial the legal significance of a release.
We approve the analysis by the Superior Court of the indemnity agreement. 321 A.2d 345 (1973). The agreement clearly and unequivocally requires the contractor to indemnify the owner and the prime contractor against any liability for their own negligence, respectively. In brief, the agreement meets the tests stated in All-State Inv. and Sec. Agcy., Inc. v.…
2Cases cited3 opinions
- State v. Interstate Amiesite CorporationSupreme Court of Delaware · 1972
- Warburton v. Phoenix Steel CorporationSuperior Court of Delaware · 1974
- All-State Investigation & Security Agency, Inc. v. Turner Construction Co.Supreme Court of Delaware · 1972
3Cited by9 opinions
- Indiana State Highway Commission v. ThomasIndiana Court of Appeals · 1976
- J. A. Jones Construction Co. v. City of DoverSuperior Court of Delaware · 1977
- Sweetman v. Strescon Industries, Inc.Superior Court of Delaware · 1978
- Nutt v. GAF Corp.Superior Court of Delaware · 1987
- Cumberbatch v. Board of Trustees, Delaware Technical & Community CollegeSuperior Court of Delaware · 1978
4 more not listed; retrieve them via the Exa API.