This case arises from a construction contract. Judith and A.J. Dunlap hired Tremont Construction Company, Inc., to build a house for $771,000. After finishing the project, Tremont filed suit claiming the Dunlaps failed to pay some construction costs. It alleged causes of action for breach of contract, foreclosure of a mechanic’s lien, and quantum meruit. In their answer, the Dunlaps raised, among other things, accord and satisfaction as an affirmative defense. They also counterclaimed for defamation of title and breach of warranty. The court granted the Dunlap’s motion for partial…

2Cases cited4 opinions

  1. Davis v. Piedmont Engineers, Architects & Planners, P.A.Court of Appeals of South Carolina · 1984
  2. Florence City-County Airport Commission v. Air Terminal Parking Co.Court of Appeals of South Carolina · 1984
  3. Redmond v. StrangeSupreme Court of South Carolina · 1943
  4. Mercury Marine Division, of Brunswick Corp. v. CostasCourt of Appeals of South Carolina · 1986

3Cited by14 opinions

  1. Ecclesiastes Production Ministries v. Outparcel Associates, LLCCourt of Appeals of South Carolina · 2007
  2. Historic Charleston Holdings, LLC v. MallonSupreme Court of South Carolina · 2009
  3. Linda Mc Co., Inc. v. ShoreSupreme Court of South Carolina · 2010
  4. Acierno v. Worthy Brothers Pipeline Corp.Supreme Court of Delaware · 1995
  5. APAC Carolina, Inc. v. Town of AllendaleCourt of Appeals for the Fourth Circuit · 1994