Bostwick-Batterson Co. v. United States
United States Court of Claims
1Opinion of the CourtWhitaker, Judge
On September 4, 1953, plaintiff was awarded a contract for the manufacture of 165,000 pairs of khaki Army trousers. The contract was performed by plaintiff’s subcontractor, Keystone Coat & Apron Mfg. Corp., which is hereinafter referred to as Keystone. This suit arises out of plaintiff’s claim for increased costs resulting from packing difficulties and an assessment by defendant against plaintiff for the use of government furnished materials in excess of the contract allowances.
We shall consider first plaintiff’s claim arising out of the packing difficulties.
The specifications required that…
2Cases cited2 opinions
- Keystone Coat & Apron Mfg. Corp. v. United StatesUnited States Court of Claims · 1960
- Poloron Products, Inc. v. United StatesUnited States Court of Claims · 1953
3Cited by5 opinions
- Laburnum Construction Corporation v. The United StatesUnited States Court of Claims · 1963
- Marley v. United StatesUnited States Court of Claims · 1970
- Philadelphia Regent Builders, Inc. v. United StatesUnited States Court of Claims · 1980
- Transamerica Insurance ex rel. Stroup Sheet Metal Works v. United StatesUnited States Court of Federal Claims · 1993
- Marley v. United StatesCourt of Appeals for the First Circuit · 1970