H. W. Ivey Construction Co. v. Southwest Steel Products
Court of Appeals of Georgia
1Opinion of the Court
Bell, Presiding Judge.
The petition under consideration did not allege compliance with the following conditions present in the bond involved in this suit. “No suit or action shall be commenced hereunder by any claimant. . . Unless claimant shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount .claimed and the name of the party to…
2Cases cited21 opinions
- Frazier v. Southern Railway CompanySupreme Court of Georgia · 1946
- Hulsey v. Interstate Life & Accident InsuranceSupreme Court of Georgia · 1950
- American Surety Co. v. Small Quarries Co.Supreme Court of Georgia · 1923
- Ford v. S. A. Lynch CorporationCourt of Appeals of Georgia · 1949
- Hannah v. Lovelace-Young Lumber Co.Supreme Court of Georgia · 1925
16 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Fulton National Bank v. YoungCourt of Appeals of Georgia · 1970