C. W. Stark Lumber Co. v. Sether
Supreme Court of Minnesota
1Opinion of the Court
YETKA, Justice.
This is an action to foreclose a mechanics lien by a materialman who supplied lumber to a construction company, which at the time of the first delivery of materials was the vendor in an unrecorded executory contract for the sale of real property. The construction company used the lumber to construct a house on land which it then sold to the vendees. The construction company failed to pay the materialman, who thereafter sought to foreclose a mechanics lien. The trial court granted the vendees’ motion for partial summary judgment on the grounds that the materialman had failed to…
2Cases cited4 opinions
- Shaughnessy v. EidsmoSupreme Court of Minnesota · 1946
- Atkins v. LittleSupreme Court of Minnesota · 1871
- Nasseff v. SchoeneckerSupreme Court of Minnesota · 1977
- Carey-Lombard Lumber Co. v. BierbauerSupreme Court of Minnesota · 1899
3Cited by8 opinions
- Dolder v. GriffinSupreme Court of Minnesota · 1982
- Minnesota Wood Specialties, Inc. v. MattsonSupreme Court of Minnesota · 1978
- Mill City Heating & Air Conditioning Co. v. NelsonSupreme Court of Minnesota · 1984
- Louie's Floor Covering, Inc. v. DePhillips Interests, Ltd.Supreme Court of Iowa · 1985
- Marque Plumbing, Inc. v. BarrisCourt of Appeals of Minnesota · 1986