Legal Opinion

P.R. Contractors, Inc. v. United States

United States Court of Federal Claims

Decided May 31, 2007No. 03-30CPublishedCited by 1 opinion

1Opinion of the Court

OPINION

WILLIAMS, Judge.

Plaintiff, P.R. Contractors, Inc. (PR), seeks to recover additional costs totaling $865,156 *623that it claims to have incurred under its contract with the Army Corps of Engineers (Corps) for a levee enlargement in Louisiana (the Contract). Plaintiffs claim includes five components: 1) labor wage rate variances, 2) increased trucking costs, 3) material shrinkage, 4) quantity under-run and 5) additional fill due to settlement.

Plaintiff failed to prove that during negotiations the Corps agreed to compensate it for any increased labor or trucking costs it might incur above…

2Cases cited19 opinions

  1. McAbee Construction, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 1996
  2. Scott Timber Company v. United StatesCourt of Appeals for the Federal Circuit · 2003
  3. Foley Company v. United StatesCourt of Appeals for the Federal Circuit · 1993
  4. Barron Bancshares, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2004
  5. Urban Data Systems, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1983

14 more not listed; retrieve them via the Exa API.

3Cited by1 opinion

  1. Ironclad/EEI v. United StatesUnited States Court of Federal Claims · 2007

Showing a preview — retrieve the full document via the Exa API.