BARRETT, Circuit Judge.

The Public Service Company of Colorado (PSC) and the Colorado River Water Conservation District (CRWCD), an intervenor in the administrative proceedings, petition this Court for review of two orders of the Federal Energy Regulatory Commission (FERC). In its “Order Providing For Hearing,” Docket No. HB24-63-3, February 10, 1982, 18 FERC 1161,110, FERC determined that PSC was liable to pay the United States for headwater benefits received at PSC’s Shoshone Hydroelectric Plant from the United States’ Green Mountain Reservoir, pursuant to section 10(f) of the Federal Power…

2Cases cited33 opinions

  1. Tennessee Valley Authority v. HillSupreme Court of the United States · 1978
  2. Morton v. MancariSupreme Court of the United States · 1974
  3. United States v. Borden Co.Supreme Court of the United States · 1939
  4. First Iowa Hydro-Electric Cooperative v. Federal Power CommissionSupreme Court of the United States · 1946
  5. Strickler v. City of Colorado SpringsSupreme Court of Colorado · 1891

28 more not listed; retrieve them via the Exa API.

3Cited by1 opinion

  1. Public Service Company of Colorado v. Federal Energy Regulatory Commission, Colorado River Water Conservation District v. Federal Energy Regulatory Commission, Public Service Company of Colorado v. Federal Energy Regulatory CommissionCourt of Appeals for the Tenth Circuit · 1985