City of Wahpeton v. Drake-Henne, Inc.

North Dakota Supreme Court

Decided February 1, 1974No. Civ. 8870Published

1ConcurrencePaulson, J.

Syllabus to Opinion of Chief Justice Erickstad

1. Although backfill compaction was deficient at the time the certificate of completion was signed by the project engineer, *902the City did not waive compliance with the contract specifications by the engineer’s certification of completion and accordingly is not barred from recovering for defects resulting from the contractor’s failure to perform according to the specifications, when defects were discovered during the one-year period as provided for in I(H)3.(b) of the contract.

2. The pertinent provisions of the contract in the instant case limit…

2Cases cited20 opinions

  1. City of Midland v. WallerTexas Supreme Court · 1968
  2. Condon v. KemperSupreme Court of Kansas · 1891
  3. City of Granville v. Kovash, IncorporatedNorth Dakota Supreme Court · 1962
  4. McConnell v. L. C. L. Transit Co.Wisconsin Supreme Court · 1969
  5. Hofer v. WM Scott Livestock CompanyNorth Dakota Supreme Court · 1972

15 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API