National Union Fire Insurance v. David A. Bramble, Inc.
Court of Appeals of Maryland
1Opinion of the Court
BATTAGLIA, Judge.
In the present case we are asked to determine the effect of a general contractor’s payment bond surety’s failure to fulfill a contractual provision requiring it to answer a subcontractor’s payment claim within 45 days after receiving that claim. We determine that the language of the payment bond requires the sureties to delineate those portions of the claim that they intend to dispute within the 45-day period and that, under the language of the bond, a failure to do so results in the entirety of the claim being undisputed. We hold that Wadsworth Golf Construction Company of…
2Cases cited23 opinions
- General Motors Acceptance Corp. v. DanielsCourt of Appeals of Maryland · 1985
- Bausch & Lomb Inc. v. Utica Mutual InsuranceCourt of Appeals of Maryland · 1993
- Cheney v. Bell National Life InsuranceCourt of Appeals of Maryland · 1989
- Atlantic Contracting & Material Co. v. Ulico Casualty Co.Court of Appeals of Maryland · 2004
- Dahl v. Brunswick Corp.Court of Appeals of Maryland · 1976
18 more not listed; retrieve them via the Exa API.
3Cited by11 opinions
- Toney v. Chester County HospitalSupreme Court of Pennsylvania · 2011
- Tomran, Inc. v. PassanoCourt of Appeals of Maryland · 2006
- Questar Builders, Inc. v. CB Flooring, LLCCourt of Appeals of Maryland · 2009
- Sloan & Co. v. Liberty Mutual InsuranceCourt of Appeals for the Third Circuit · 2011
- Sheet Metal Workers' Local Union No. 100 Washington, D.C. Area Pension Fund v. Western Surety Co.District Court, D. Maryland · 2016
6 more not listed; retrieve them via the Exa API.