Kirby v. Kenyon-Noble Lumber Co.
Montana Supreme Court
1Opinion of the CourtJustice Daly
Plaintiff Jack Kirby appeals from a judgment of the district court, Gallatin County, awarding damages for breach of contract. Kirby asserts the judgment awarded is inadequate and conflicts with the court’s own findings and conclusions.
Jack and Barbara Kirby (Kirby), entered into a contract with Kenyon-Noble Lumber Co., Bozeman, Montana (contractor), on October 20, 1969 to build a home on their property near Ennis, Montana. The contractor’s work was to be completed on or about December 1, 1969. The contract provided for Kirby to pay $18,883.45 and to furnish the excavation for the foundation…
2Cases cited3 opinions
- Schmauch v. JohnstonOregon Supreme Court · 1976
- Mitchell v. CarlsonMontana Supreme Court · 1957
- Haggerty v. SelscoMontana Supreme Court · 1975
3Cited by7 opinions
- Stensvad v. MINERS & MERCHANTS BANK, ETC.Montana Supreme Court · 1982
- Carriger v. BallengerMontana Supreme Court · 1981
- Martin Development Co. v. Keeney Construction Co.Montana Supreme Court · 1985
- Frank L. Pirtz Construction, Inc. v. Hardin Town Pump, Inc.Montana Supreme Court · 1984
- Sack v. A v. Design, Inc.Montana Supreme Court · 1984
2 more not listed; retrieve them via the Exa API.