Legal Opinion

G. Schwartz & Co. v. United States

United States Court of Claims

Decided May 29, 1939No. 43096PublishedCited by 2 opinions

1Opinion of the CourtWilliams, Judge

Plaintiff seeks to recover the sum of $11,609.71 as damages arising out of an alleged breach of a contract between plaintiff and the defendant for the construction of a post-office building at Rochester, Minnesota.

The amount claimed consists! of three separate items. '

1. $8,600.00, the salvage value of certain buildings on -the site of the work which the defendant permitted prior owners to remove therefrom, it being contended that under the contract plaintiff was to receive such buildings as a part of the contract price.

2. $2,606.59, additional expenses incurred by the plaintiff in the…

2Cases cited4 opinions

  1. Harvey v. United StatesSupreme Court of the United States · 1882
  2. United States v. MuellerSupreme Court of the United States · 1885
  3. Mueller v. United StatesUnited States Court of Claims · 1884
  4. Proffit v. United StatesUnited States Court of Claims · 1907

3Cited by2 opinions

  1. Dana Corp. v. United StatesUnited States Court of Claims · 1972
  2. Pfotzer v. United StatesUnited States Court of Claims · 1948

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API