1Opinion of the CourtLittleton, Judge

Plaintiffs’ total claim of $136,431.38 is made up of an alleged cost of $60,257.50 due to inefficiency of alleged unqualified labor supplied by the defendant and paid for by plaintiffs; excessive and unnecessary costs for overhead expense in the amount of $32,032.00 at $246.40 a day for the! period of 130 days’ delay, alleged to have been caused by the defendant which, it is alleged, was due to inefficient labor, unreasonable interference with the work and unreasonable inspection and supervision by the defendant’s inspectors and engineers; alleged unnecessary expense and loss of $2,564.45 for…

2Cited by2 opinions

  1. Arundel Corp. v. United StatesUnited States Court of Claims · 1942
  2. Frazier-Davis Construction Co. v. United StatesUnited States Court of Claims · 1943