City of Crawfordsville v. Johnson
Indiana Supreme Court
From the Montgomery Circuit Court.
1Opinion of the CourtPettit, J.
This was a suit by the appellees against the appellant, to enforce the lien of sub-contractors under the mechanic’s lien law. There are but two questions in the case:
1. Can a sub-contractor secure a lien on the building and ground on which it is erected, by filing the proper notice, within the legal time, but after the owner has fully paid the contractor all that was due to him on the contract? In the thoroughly and fully considered case of Colter v. Frese, 45 Ind. 96, this question was ruled in the affirmative, and we adhere to that ruling.
2. "Was the notice' given sufficiently definite and…
2Cases cited4 opinions
- Colter v. FreseIndiana Supreme Court · 1873
- Lindley v. CrossIndiana Supreme Court · 1869
- Howell v. ZerbeeIndiana Supreme Court · 1866
- City of Crawfordsville v. IrwinIndiana Supreme Court · 1874
3Cited by15 opinions
- Moore-Mansfield Construction Co v. Indianapolis, Newcastle & Toledo Railway Co.Indiana Supreme Court · 1913
- Clark v. HueyIndiana Court of Appeals · 1895
- City of Crawfordsville v. BrundageIndiana Supreme Court · 1877
- McNamee v. RauckIndiana Supreme Court · 1891
- Hill v. SloanIndiana Supreme Court · 1877
10 more not listed; retrieve them via the Exa API.