Central Maine Power Co. v. Public Utilities Commission
Supreme Judicial Court of Maine
1Opinion of the Court
WATHEN, Justice.
On June 29, 1981, Central Maine Power Company (“CMP”, “Company”) filed with the Commission proposed new rate schedules pursuant to 35 M.R.S.A. § 64 (Supp. 1982-83). The proposed rates were designed to produce a net increase in annual operating revenues equal to 15.3%, or $55,-000,000, based upon a 1981 test year.
After extensive public hearings, the Commission entered its Decision and Order on March 27,1982. That Order disallowed and rejected the schedule of proposed rates filed by CMP and authorized the Company to file a substitute rate schedule designed “to increase test year…
2Cases cited14 opinions
- Federal Power Commission v. Hope Natural Gas Co.Supreme Court of the United States · 1944
- Federal Power Commission v. Natural Gas Pipeline Co.Supreme Court of the United States · 1942
- Bluefield Water Works & Improvement Co. v. Public Service CommissionSupreme Court of the United States · 1923
- Pacific Telephone & Telegraph Co. v. Public Utilities CommissionCalifornia Supreme Court · 1965
- New England Telephone & Telegraph Co. v. Public Utilities CommissionSupreme Judicial Court of Maine · 1978
9 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- State Ex Rel. Associated Natural Gas Co. v. Public Service CommissionMissouri Court of Appeals · 1985
- Imagineering, Inc. v. Superintendent of InsuranceSupreme Judicial Court of Maine · 1991
- Maine Water Co. v. Public Utilities CommissionSupreme Judicial Court of Maine · 1984
- Trull Nursing Home, Inc. v. State Department of Human ServicesSupreme Judicial Court of Maine · 1983
- MAINE AFL-CIO v. Superintendent of Ins.Supreme Judicial Court of Maine · 1991
14 more not listed; retrieve them via the Exa API.