Lent's, Inc. v. Santa Fe Engineers, Inc.
Court of Appeals of Washington
1Opinion of the CourtSwanson, J.
This appeal involves the validity of an arbitration award vacated by the trial court on the ground that it was not rendered within 30 days of the close of the arbitration hearings as required by RCW 7.04.090. Appellants, Santa Fe Engineers, Inc., and Howard Electric Co., contend that the award was rendered in a timely manner or, in the alternative, that respondent, Lent's, Inc., waived any objection it had to the timeliness of the award. In a cross appeal, Lent's contends that the trial court erred in not holding that the arbitration award demonstrated on its face an error in the application…
2Cases cited8 opinions
- Goble v. Central Security Mutual InsuranceAppellate Court of Illinois · 1970
- Fagnani v. Integrity Finance CorporationSuperior Court of Delaware · 1960
- BALFOUR, GUTHRIE AND COMPANY, LIMITED v. Commercial Metals Co.Washington Supreme Court · 1980
- School District No. 5 v. SageWashington Supreme Court · 1896
- Marsala v. Valve Corporation of AmericaSupreme Court of Connecticut · 1969
3 more not listed; retrieve them via the Exa API.
3Cited by11 opinions
- Marine Enterprises, Inc. v. Security Pacific Trading Corp.Court of Appeals of Washington · 1988
- Westmark Properties, Inc. v. McGuireCourt of Appeals of Washington · 1989
- Hanson v. ShimCourt of Appeals of Washington · 1997
- Lindon Commodities, Inc. v. Bambino Bean Co.Court of Appeals of Washington · 1990
- Graceman v. GoldsteinCourt of Special Appeals of Maryland · 1992
6 more not listed; retrieve them via the Exa API.