Legal Opinion

Oliver Const. Co. v. Crawford

Mississippi Supreme Court

Decided April 19, 1926No. 25592PublishedCited by 10 opinions

1Opinion of the Court

Ethridge J.,

delivered the opinion of the court.

The appellee was plaintiff below, and sued the appellant on its contractor’s bond executed under the provisions of chapter 217, Laws of 1918, which requires a contractor of public works of the- kind here contracted for to execute a bond, which provides:

“That auy person entering' into a formal contract with this state, any county thereof, municipality therein, or any political subdivision whatsoever therein, for the construction of any building or work or the doing of repairs, shall be required before commencing same to execute the usual bond,…

2Cases cited2 opinions

  1. Oliver Const. Co. v. DancyMississippi Supreme Court · 1925
  2. Watkins v. United States Fidelity & Guaranty Co.Mississippi Supreme Court · 1925

3Cited by10 opinions

  1. McElrath & Rogers v. W. G. Kimmons & SonsMississippi Supreme Court · 1927
  2. United States Fidelity & Guaranty Co. v. First Nat. Bank of LincolnSupreme Court of Alabama · 1932
  3. Marquette Cement Mfg. Co. v. Fidelity & Deposit Co.Mississippi Supreme Court · 1935
  4. United States Fidelity & Guaranty Co. v. Yazoo County Ex Rel. RingsMississippi Supreme Court · 1926
  5. Western Casualty & Surety Co. v. LashSouth Dakota Supreme Court · 1940

5 more not listed; retrieve them via the Exa API.