Legal Opinion

Cassidy & Gallagher, Inc. v. United States

United States Court of Claims

Decided February 2, 1942No. 43704Published

1Opinion of the CourtJoNes, Judge

Plaintiff seeks recovery of excess costs incurred in completing a contract with the Government.

The contract called for the construction of five steel radio, masts, 125 feet in height, with concrete foundations, near Albany, New York.

The contract price was $4,639.00. The structures were to. be completed within 45 days after receipt of notice to proceed.

The plaintiff asserts that it encountered unforeseen difficulties in the way of subsurface water conditions which made it necessary to expend $2,267.50 for labor and materials above the amount originally contemplated.

For this sum it sues,…

2Cases cited3 opinions

  1. C. W. Blakeslee & Sons, Inc. v. United StatesUnited States Court of Claims · 1939
  2. Trimount Dredging Co. v. United StatesUnited States Court of Claims · 1935
  3. James Stewart & Co. v. United StatesUnited States Court of Claims · 1941

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API