Legal Opinion

N. E. Redlon Co. v. Franklin Square Corp.

Supreme Court of New Hampshire

Decided March 5, 1940No. 3135PublishedCited by 1 opinion

1Opinion of the Court

Page, J. I.

One of the purposes of the recommittal after the former opinion was to ascertain what, if any, allowance should be made to the defendant because of the substitution of damp-proofing for membrane waterproofing on the outside of the foundation walls.

At the last hearing it appeared that the plaintiff, before making its own bid to the defendant, received a bid for the waterproofing from the Western Waterproofing Company, which likewise made identical bids to other general contractors who were estimating on the defendant’s building. The Western’s estimator testified as to the process of…

2Cases cited4 opinions

  1. West v. Boston & Maine RailroadSupreme Court of New Hampshire · 1925
  2. Roberts v. Claremont Power Co.Supreme Court of New Hampshire · 1917
  3. Watkins v. Boston & Maine RailroadSupreme Court of New Hampshire · 1924
  4. Ingalls v. Maine Central RailroadSupreme Court of New Hampshire · 1928

3Cited by1 opinion

  1. Wright v. Clark Equipment Co.Supreme Court of New Hampshire · 1984

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API