Metric Construction Co. v. United States
United States Court of Claims
1Opinion of the Court
OPINION
LYDON, Judge:
In this “direct access” construction contract case, filed pursuant to Section 10(a) of the Contract Disputes Act of 1978, 41 U.S.C. Sec. 609(a)(1) (Supp. V 1981) (CDA), plaintiff seeks to recover a fee it paid, or.is required to pay, to a third party indemnitor of a surety company which, it is alleged, agreed to issue required performance and payment bonds on the strength of said indemnity agreement, in connection with plaintiff’s bid and subsequent award of a contract by the Department of the Navy, Naval Facilities Engineering Command (NFEC). Plaintiff’s position is that…
2Cases cited18 opinions
- United States v. KingSupreme Court of the United States · 1969
- Church of the Holy Trinity v. United StatesSupreme Court of the United States · 1892
- Paragon Energy Corp. v. United StatesUnited States Court of Claims · 1981
- Paul E. Lehman, Inc. v. United StatesUnited States Court of Claims · 1982
- Skelly v. United StatesUnited States Court of Claims · 1982
13 more not listed; retrieve them via the Exa API.
3Cited by39 opinions
- Contract Cleaning Maintenance, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1987
- Mega Construction Co. v. United StatesUnited States Court of Federal Claims · 1993
- Youngdale & Sons Construction Co. v. United StatesUnited States Court of Federal Claims · 1993
- Tunica-Biloxi Tribe of La. v. United StatesDistrict Court, District of Columbia · 2008
- Modeer v. United StatesUnited States Court of Federal Claims · 2005
34 more not listed; retrieve them via the Exa API.