Smoky Hills Wind Project II v. City of Independence, Missouri

Court of Appeals for the Eighth Circuit

Decided May 2, 2018No. 17-1091; 17-1171PublishedCited by 2 opinions

1Opinion of the Court

ERICKSON, Circuit Judge.

This case involves a "Renewable Energy Purchase Agreement" ("REPA") that resulted from arms-length bargaining between parties with longstanding experience and expertise in the generation and marketing of electrical energy. Smoky Hills Wind Project II, LLC ("Smoky II"), operates a wind farm generating wind energy which it supplies to various customers, known in the energy business as "off-takers." Smoky II is an indirect subsidiary of Enel Green Power North America, Inc., whose parent company is Enel Green Power, SpA., headquartered in Italy. The City of Independence,…

2Cases cited12 opinions

  1. Marquis v. State Farm Fire & Casualty Co.Supreme Court of Kansas · 1998
  2. Warner Bros. Entertainment v. X One X ProductionsCourt of Appeals for the Eighth Circuit · 2011
  3. Waste Connections of Kansas, Inc. v. Ritchie Corp.Supreme Court of Kansas · 2013
  4. Liggatt v. Employers Mutual Casualty Co.Supreme Court of Kansas · 2002
  5. PFS Distribution Co. v. RaduechelCourt of Appeals for the Eighth Circuit · 2009

7 more not listed; retrieve them via the Exa API.

3Cited by2 opinions

  1. Ann Eleanor Ploetz v. Morgan Stanley Smith BarneyCourt of Appeals for the Eighth Circuit · 2018
  2. Nancy Axline v. 3M CompanyCourt of Appeals for the Eighth Circuit · 2021

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API