George v. Goldman
Massachusetts District Court, Appellate Division
1Opinion of the CourtBarron, J.
This is an action of contract to recover the balance of monies due (1) for the construction of a six room brick house under an oral contract; (2) for furnishing extras; (3) for structural changes under an oral contract during the erection of said house. The defendants denied the plaintiff’s allegations.
The court (Tomasello, J.) found for the plaintiff for $1,968.46, the balance alleged due for the construction under the contract, and for $676.00 for extras and for the defendants on the claim by the plaintiff of $1,235.00 for monies alleged due for structural changes.
Evidence was introduced by…
2Cases cited5 opinions
- Patterson v. CiborowskiMassachusetts Supreme Judicial Court · 1931
- First National Stores Inc. v. H. P. Welch Co.Massachusetts Supreme Judicial Court · 1944
- Griffin v. RudnickMassachusetts Supreme Judicial Court · 1937
- Commissioners of Woburn Cemetery v. Treasurer of WoburnMassachusetts Supreme Judicial Court · 1946
- Hill v. Creditors National Clearing HouseMassachusetts Supreme Judicial Court · 1935
3Cited by2 opinions
- Davis v. City of WorcesterMassachusetts District Court, Appellate Division · 1995
- Deerfield Forest Apartments/U.S. Shelter Corp. v. GrigorianMassachusetts District Court, Appellate Division · 1987