Public Utility District No. 1 v. Federal Power Commission
Court of Appeals for the Ninth Circuit
1Opinion of the Court
POPE, Circuit Judge.
The Federal Power Commission issued to Public Utility District No. 1 of Chelan County, Washington, here called Chelan, a license under § 4(e) of the Federal Power Act, Title 16 U.S.C.A. § 797(e), for the construction and operation of what was designated as the Rocky Reach Hydroelectric Power Project on the Columbia River. Public Utility District No. 1 of Douglas County, Washington, here called Douglas, holder of a preliminary permit for a power site known as the Wells Project, some 40 miles upstream from the Rocky Reach site, intervened in the proceedings before the…
2Cases cited15 opinions
- Universal Camera Corp. v. National Labor Relations BoardSupreme Court of the United States · 1951
- United States v. L. A. Tucker Truck Lines, Inc.Supreme Court of the United States · 1952
- Wong Yang Sung v. McGrathSupreme Court of the United States · 1950
- Federal Communications Commission v. Sanders Bros. Radio StationSupreme Court of the United States · 1940
- Scripps-Howard Radio, Inc. v. Federal Communications CommissionSupreme Court of the United States · 1942
10 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Stieberger v. HecklerDistrict Court, S.D. New York · 1985
- Public Utility District No. 1 Of Douglas County, State Of Washington v. Federal Power CommissionCourt of Appeals for the Ninth Circuit · 1957