Respondents sought damage^ from appellants for breach of contract. A trial without jury resulted in judgment in favor of respondents. Appellants contend the district court erred in (1) interpreting and applying a liquidated damages clause; (2) computing damages; and, (3) failing to order a .new trial. We disagree.

On June 4, 1971, appellant Spinella entered into a construction contract with respondent B-Neva, Inc., respondent Nevada Allied Industries, Inc.’s predecessor in interest. The contract provided for Spinella to furnish the labor and materials required to pave and place drainage…

3Cases cited5 opinions

  1. Sanguinetti v. StreckerNevada Supreme Court · 1978
  2. Oregon, State Highway Com'n v. DeLong Corp.Court of Appeals of Oregon · 1972
  3. Lyon v. Walker Boudwin Construction Co.Nevada Supreme Court · 1972
  4. Thompson v. HerrmannNevada Supreme Court · 1975
  5. Lawson v. DurantSupreme Court of Kansas · 1974

4Cited by2 opinions

  1. Vankirk v. Green Construction Co.West Virginia Supreme Court · 1995
  2. A. Miner Contracting, Inc. v. Toho-Tolani County Improvement DistrictCourt of Appeals of Arizona · 2013

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API