SILAK, Justice.
This is an appeal by Cogeneration, Inc. (Cogeneration) from a district court judgment in favor of Idaho Power Company (Idaho Power) in a breach of contract action. We affirm.
I
FACTUAL AND PROCEDURAL BACKGROUND
A. Factual Background
Cogeneration held a Federal Energy Regulatory Commission (FERC) license to construct a hydroelectric facility at Auger Falls on the Snake River. Under federal law, Idaho Power was obligated to enter into an agreement with Cogeneration for the purchase of power from the Auger Falls plant after its completion.
In January 1992, Idaho Power and Cogeneration…
2Cases cited32 opinions
- Sun Valley Shopping Center, Inc. v. Idaho Power Co.Idaho Supreme Court · 1991
- Idaho First National Bank v. Bliss Valley Foods, Inc.Idaho Supreme Court · 1992
- O'DELL v. BasabeIdaho Supreme Court · 1991
- Marshall v. BlairIdaho Supreme Court · 1997
- Watson v. Idaho Falls Consolidated Hospitals, Inc.Idaho Supreme Court · 1986
27 more not listed; retrieve them via the Exa API.
3Cited by55 opinions
- Shawver v. Huckleberry Estates, L.L.C.Idaho Supreme Court · 2004
- Potlatch Education Ass'n v. Potlatch School District No. 285Idaho Supreme Court · 2010
- Spanish Oaks, Inc. v. Hy-Vee, Inc.Nebraska Supreme Court · 2003
- O'Connor v. Harger Construction, Inc.Idaho Supreme Court · 2008
- Bakker v. Thunder Spring-Wareham, LLCIdaho Supreme Court · 2005
50 more not listed; retrieve them via the Exa API.