New Valley Corp. v. United States
United States Court of Federal Claims
1Opinion of the Court
Amended and Corrected Opinion and Order 1
WEINSTEIN, Judge.
Plaintiff seeks damages, for breach of contract or a taking, arising from the government’s failure to launch a commercial payload due to revisions to the nation’s space policy following the shuttle “Challenger” disaster. Defendant has moved to dismiss this action because plaintiff did not exhaust the contractual administrative disputes process, or, in the alternative, because plaintiff contractually waived all claims for non-performance. After oral argument, defendant’s motion to dismiss is granted.
Facts
The National Aeronautics and…
2Cases cited32 opinions
- Lynch v. United StatesSupreme Court of the United States · 1934
- Franklin v. MassachusettsSupreme Court of the United States · 1992
- Connolly v. Pension Benefit Guaranty CorporationSupreme Court of the United States · 1986
- United States v. National Treasury Employees UnionSupreme Court of the United States · 1995
- United States v. Carlo Bianchi & Co.Supreme Court of the United States · 1963
27 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- New Valley Corporation v. United StatesCourt of Appeals for the Federal Circuit · 1997
- New Valley Corp. v. United StatesUnited States Court of Federal Claims · 2005
- New Valley Corporation v. United StatesCourt of Appeals for the Federal Circuit · 1997