McShain v. United States

United States Court of Claims

Decided November 14, 1938No. 43834PublishedCited by 1 opinion

1Opinion of the CourtWhaley, Judge

This suit arises out of a contract between the plaintiff and the defendant dated February 6, 1933, for the construction by the plaintiff for the defendant of a hospital in the Navy Yard at Philadelphia, Pa. On September 14, 1933, the defendant notified the plaintiff that the remainder of the contract work would be done in conformity with the requirements of the National Industrial Recovery Act, 48 Stat. 195; 15 U. S. C. A. Sec. 102, 712. On November 9, 1933, a supplemental agreement was executed whereby the plaintiff agreed that further performance of the original contract would be carried on…

2Cases cited2 opinions

  1. George Leary Construction Co. v. United StatesUnited States Court of Claims · 1927
  2. Pneumatic Gun-Carriage & Power Co. v. United StatesUnited States Court of Claims · 1901

3Cited by1 opinion

  1. Johnstown Coal & Coke Co. of New York, Inc. v. United StatesUnited States Court of Claims · 1944

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API