Redman Development Corp. v. Pollard
Court of Appeals of Georgia
1Opinion of the Court
Evans, Judge.
Redman Development Corporation, a general con tractor, entered into a written contract with Henry J. Pollard and James W. Wheeler, a partnership doing business as Pollard & Moss Construction Company, as sub-contractor, to do the framing of an apartment complex. Any changes in the work required written work orders. During the progress of the work a controversy arose as. to payments, particularly for extra work performed; and a purported settlement and change order was entered.
Pollard & Moss Construction Company finally left the job, ostensibly because Redman refused to pay for…
2Cases cited9 opinions
- Worthy v. StateSupreme Court of Georgia · 1937
- Norman v. McMillanSupreme Court of Georgia · 1921
- Shubert v. SpeirSupreme Court of Georgia · 1946
- Beck v. Thompson & Taylor Spice Co.Supreme Court of Georgia · 1899
- King v. LewisSupreme Court of Georgia · 1939
4 more not listed; retrieve them via the Exa API.
3Cited by8 opinions
- Kwickie/Flash Foods, Inc. v. Lakeside Petroleum, Inc.Court of Appeals of Georgia · 2000
- Eldon Industries, Inc. v. Paradies and CompanyDistrict Court, N.D. Georgia · 1975
- Quealy v. AndersonUtah Supreme Court · 1986
- Gilbert v. PowellCourt of Appeals of Georgia · 1983
- Walker v. Joanna M. Knox & Associates, Inc.Court of Appeals of Georgia · 1974