1Opinion of the CourtMhbphy, J.

The plaintiff sued the defendant to recover for the installation of a sprinkler system in a Greenwich school. The defendant was the general contractor. Its contract with the Greenwich board of education did not include the sprinkler system. The plaintiff was the plumbing subcontractor. Its subcontract with the defendant stated that the plaintiff would do the plumbing work, “including the Sprinkler System.” The plaintiff alleged that the system was included in its written subcontract upon the express oral agreement of the defendant that it would reimburse the plaintiff for the price of the…

2Cases cited9 opinions

  1. Batter Building Materials Co. v. KirschnerSupreme Court of Connecticut · 1954
  2. Boucher v. GodfreySupreme Court of Connecticut · 1935
  3. Harris v. ClintonSupreme Court of Connecticut · 1955
  4. W. G. Maltby, Inc. v. Associated Realty Co.Supreme Court of Connecticut · 1932
  5. Gray v. GreenblattSupreme Court of Connecticut · 1931

4 more not listed; retrieve them via the Exa API.

3Cited by7 opinions

  1. Panaroni v. JohnsonSupreme Court of Connecticut · 1969
  2. Randolph Construction Co. v. Kings East CorporationSupreme Court of Connecticut · 1973
  3. E & F CONSTRUCTION CO. v. Rissil Construction Associates, Inc.Supreme Court of Connecticut · 1980
  4. Jaybe Construction Co. v. Beco, Inc.Connecticut Appellate Court · 1965
  5. Sonnichsen v. StreeterConnecticut Appellate Court · 1967

2 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API