Chicago, Milwaukee, St. Paul & Pacific Railroad
United States Court of Claims
1Opinion of the Court
Transportation of freight. On a memorandum report by the commissioner stating that the parties had reached agreement at a pretrial conference, it was ordered that judgment for the plaintiff be entered for $15,833.06.
Pay and Allowances
On stipulations by the parties based on the decisions of the court in Tanner v. United States, 129 C. Cls. 892, cert. denied 350 U. S. 842; Seagrave v. United States, 131 C. Cls. 790; Hyde v. United States, 134 C. Cls. 690, and Stevanus v. United States, 138 C. Cls. 149, judgments were entered for the respective plaintiffs for the amounts stated in the several…
2Cases cited3 opinions
- Seagrave v. United StatesUnited States Court of Claims · 1955
- Stevanus v. United StatesUnited States Court of Claims · 1957
- Hyde v. United StatesUnited States Court of Claims · 1956